LÏEF Development
SABS Bid TrackerLÏEF Development · Internal
← Back to Projects

SABS Bid

Build in Chandler — ADU (Strata Plan 957)

Bidding

Latest Bid

$194,750

Square Footage

1,025

Units

1

Scope Class

Full Project

Estimate SLA

Day 69 / 10OVERDUE

Project Lifecycle

Received
Takeoff
Bidding
Submitted
Awarded
Start

Project Brief

Chandler, AZ — lot address TBD. Single-story ADU/detached residence built to Strata Plan 957 (25'-0" x 41'-0"). 957 SF livable / 1,025 SF under roof. Layout: 2 BR, 2 BA, Kitchen, Great Room, Covered Porch. Gable roof as drawn (may change to flat/lean-to). GC: Armstrong Construction Group (ROC #339747). Requested by Valeria Zavala, Strata (val@strataus.com).

Work Scope

LÏEF is the all-inclusive builder on a single-story 1,025 SF ADU built to Strata Plan 957 (25'x41', 2BR/2BA) in Chandler for Val Zavala's client. Self-perform SABS scope: foundation, LÏEF Block foam framing, SABScrete application; subbed scope: plumbing and electrical plus finish allowances — all rolled under Armstrong Construction Group as GC of record (ROC #339747). Bid $194,750 all-in ($190/SF midpoint of $180–$200/SF): $163,930 direct + 8% GC + 10% OH&P. Roof priced as gable-as-drawn even though it may shift to flat/lean-to.

Scope Summary

Full build: foundation, SABS foam framing, SABScrete application, plumbing, electrical on single-story ADU per Strata Plan 957.

Internal Notes

Primary ContactVal's client (confirmed fine as-is by Jesse 2026-04-14)

Bid PDF dated Feb 27, 2026 (Page 1 of 3). All-inclusive: SABS material + labor, all trades, GC, OH&P. Build range $184,500-$205,000. Client trying to understand total build cost with SABS. Roof may shift to flat/lean-to but priced as-drawn. Primary contact remains 'Val's client' per Jesse 2026-04-14. Source: Build-In-Chandler/Chandler-ADU-Bid-Estimate.pdf (PDF extraction 2026-04-14), EMAIL-THREAD.md, STRATA-LEAD-LIST.md item 8. Jesse confirmation 2026-04-14.

Bid Versions

Bid EstimateFeb 27, 2026

All-inclusive bid @ $190/SF midpoint of $180-$200/SF build range. Direct Cost Subtotal $163,930 + GC 8% $13,114 + OH&P 10% $17,704 = $194,750. Quoted Items Subtotal $118,900 + Finish Allowances Subtotal $45,030.

$194,750