SABS Bid
Canyon Corporate Center
2512 W Dunlap Avenue
Latest Bid
$2,041,596
Square Footage
179,740
Units
177
Scope Class
Drywall Only
Estimate SLA
Project Lifecycle
Project Brief
Large commercial interior remodel at 2512 W Dunlap Ave, Phoenix. 179,740 SF / 177 units / 32,405 LF of wall framing across 7 wall types. Upward Architects.
Work Scope
LÏEF is self-performing interior metal-stud partition framing and drywall throughout a 179,740 SF / 177-unit commercial interior remodel at 2512 W Dunlap (Trillium / Armstrong). Scope covers 32,405 LF of wall framing across 7 wall types: Type-X firewall assemblies retained as drawn, while non-rated walls (W3/W4/W6/W7) use a 1/4" GWB + furring mat + SABScrete topcoat system per the Rev2 split (44.2% deduction bundled vs. standard GWB). Bid is drywall-only — no SABS envelope scope — with an explicit SABScrete semi-mastic disclaimer and primer-coat-only touch-up limit. Submitted at $2.04M; plans still in City of Phoenix plan check pending final site verification.
Scope Summary
Interior partition walls + drywall throughout a 118-sheet commercial remodel. Firewall (Type X) retained; non-firewall walls use 1/4" GWB + SABScrete topcoat per Rev2 split.
Internal Notes
ONLY fully-submitted bid in portfolio. Canyon = the template every other Strata bid follows. End-client Ray Gomez @ Trillium confirmed by Jesse 2026-04-14. Plans still in City of Phoenix plan check — requires final site verification vs approved set. v3 build script exists (2026-04-14) but no v3 PDF yet. Source: Canyon-Corporate/PROJECT-INFO.md, STRATA-PIPELINE-AUDIT-2026-04-10.md (row 1), file mtimes of v0/v2/v3 build scripts. Jesse confirmation 2026-04-14.
Bid Versions
Initial bid draft from takeoff
$2,191,773
First revision per Jesse's drywall math
$2,022,054
-$169,719 vs v0 ORIGINAL
Bundles 1/4" GWB + furring mat as 44.2% deduction at non-rated walls (W3/W4/W6/W7); adds SABScrete semi-mastic disclaimer and primer-coat-only touch-up scope limit
$2,041,596
+$19,542 vs v1 Rev1